Violation Detail
Standard Cited: 19100119 E03 II Process safety management of highly hazardous chemicals.
Inspection Nr: 315298307
Citation: 02002A
Citation Type: Willful
Abatement Status: X
Initial Penalty: $70,000.00
Current Penalty: $70,000.00
Issuance Date: 09/12/2011
Nr Instances: 1
Nr Exposed: 12
Abatement Date: 04/19/2012
Gravity: 10
Report ID: 0134000
Contest Date: 09/30/2011
Final Order: 05/01/2012
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 05/01/2012 | $70,000.00 | 04/19/2012 | Willful | |
| Penalty | Z: Issued | 09/12/2011 | $70,000.00 | 10/27/2011 | Willful |
Text For Citation: 02 Item/Group: 002A Hazard: CHEMNEP
29 CFR 1910.119(e)(3)(ii): The process hazard analysis did not identify previous incidents which had a likely potential for catastrophic consequencces in the workplace: (a) Location - Direct Solvation - Building 9, Solvent Cement - Building 24 and Polyester - Building 36: On or about the time of the Inspection, the process hazard analysis (PHA) did not address the following incidents to control impacts to process equipment from powered industrial vehicles including damage to ventilation trunks, storage racks, water lines and electrical equipment. 1) In Direct Solvation on 11/4/09, a ventilation trunk was struck by a tote being lifted by a forklift. 2) In Solvent Cement on 11/2/09 a forklift struck a storage rack. 3) In Polyester Building 36, on 4/27/09, a forklift struck a water line causing it to rupture and also damaged an electrical box.