Violation Detail
Standard Cited: 19100119 E03 II Process safety management of highly hazardous chemicals.
Inspection Nr: 1546668.015
Citation: 02002
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/07/2022
Nr Instances: 1
Nr Exposed: 45
Abatement Date: 01/03/2023
Gravity:
Report ID: 0213900
Contest Date: 03/02/2022
Final Order: 11/19/2022
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 11/19/2022 | $0.00 | 01/03/2023 | Other | |
| Penalty | C: Contested | 03/03/2022 | $0.00 | 03/04/2022 | Other | |
| Penalty | Z: Issued | 02/07/2022 | $0.00 | 03/04/2022 | Other |
Text For Citation: 02 Item/Group: 002 Hazard:
29 CFR 1910.119(e)(3)(ii): The process hazard analysis did not address the identification of any previous incident which had a likely potential for catastrophic consequences in the workplace. a) Chlorine process: On or about 8/9/21 the PHA failed to address previous incidents where chlorine was released from the process. On 5/15/18 a low pressure gauge on the M Furnace failed resulting in a chlorine release requiring the assistance of the local emergency response HAZMAT team. NOTE:THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT CERTIFICATION FOR THIS ITEM. FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.