Violation Detail
Standard Cited: 19100119 J02 Process safety management of highly hazardous chemicals.
Inspection Nr: 315298307
Citation: 01015
Citation Type: Serious
Abatement Status: X
Initial Penalty: $7,000.00
Current Penalty: $6,500.00
Issuance Date: 09/12/2011
Nr Instances: 1
Nr Exposed: 12
Abatement Date: 04/19/2012
Gravity: 10
Report ID: 0134000
Contest Date: 09/30/2011
Final Order: 05/01/2012
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 05/01/2012 | $6,500.00 | 04/19/2012 | Serious | |
| Penalty | Z: Issued | 09/12/2011 | $7,000.00 | 10/27/2011 | Serious |
Text For Citation: 01 Item/Group: 015 Hazard: CHEMNEP
29 CFR 1910.119(j)(2): The employer did not establish and implement written procedures to maintain the on-going mechanical integrity of process equipment: (a) Location - Direct Solvation - Building 9: On or about the time of the Inspection, the company did not have a written mechanical integrity program that addressed the preventive maintenance, inspection and testing for pumps.