Violation Detail
Standard Cited: 19100269 M03 II Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1539931.015
Citation: 01005
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,288.00
Current Penalty: $0.00
Issuance Date: 10/26/2021
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 11/22/2021
Gravity: 10
Report ID: 0626300
Contest Date:
Final Order: 12/15/2021
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/15/2021 | $0.00 | 11/22/2021 | Serious | |
| Penalty | Z: Issued | 10/26/2021 | $12,288.00 | 11/22/2021 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.269(m)(3)(ii): The employer did not ensure that all switches, disconnectors, jumpers, taps, and other means through which known sources of electric energy might be supplied to the particular lines and equipment were de-energized/open, rendered inoperable if possible, and then did not ensure that such means were tagged to indicate that employees were at work: (a) On or about June 29, 2021, two employees installing electrical equipment were exposed to an electrical hazard when the known sources of electric energy that might be supplied to the equipment were not de-energized/open, rendered inoperable if possible, and tagged to indicate employees were at work.