Violation Detail
Standard Cited: 19100269 N05 Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1640791.015
Citation: 01003B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/18/2023
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 02/26/2024
Gravity: 10
Report ID: 0522000
Contest Date: 05/04/2023
Final Order: 01/25/2024
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 01/25/2024 | $0.00 | 02/26/2024 | Serious | |
| Penalty | C: Contested | 05/08/2023 | $0.00 | 05/05/2023 | Serious | |
| Penalty | Z: Issued | 04/18/2023 | $0.00 | 05/05/2023 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1910.269(n)(5): (Grounding for the protection of employees): Testing. The employer shall ensure that, unless a previously installed ground is present, employees test lines and equipment and verify the absence of nominal voltage before employees install any ground on those lines or that equipment. (a) On Dec. 23, 2022, employees were exposed to electric shock while repairing a downed overhead powerline in that the employer did not test the lines and equipment to verify the absence of voltage prior to performing the subsequent step of installing grounds on those lines or equipment.