Violation Detail
Standard Cited: 19260416 A01 General requirements.
Inspection Nr: 917602.015
Citation: 01002A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,000.00
Current Penalty: $4,690.00
Issuance Date: 12/09/2013
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 06/23/2014
Gravity: 10
Report ID: 0627500
Contest Date: 01/03/2014
Final Order: 06/11/2014
Related Event Code (REC): A
Emphasis:
Substance: 8870
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 06/11/2014 | $4,690.00 | 06/23/2014 | Serious | |
| Penalty | C: Contested | 01/07/2014 | $7,000.00 | 12/19/2013 | Serious | |
| Penalty | Z: Issued | 12/09/2013 | $7,000.00 | 12/19/2013 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.416(a)(1): Employees were permitted to work in proximity to electric power circuits and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means: On or about July 9, 2013, mechanical room #1 at the El Paso Airport, the employer did not ensure that employees working on fluorescent luminaire circuits were protected against electrical shock by de-energizing the circuits, exposing the employees to electrical hazards.