Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1237520.015
Citation: 01002
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,149.00
Current Penalty: $6,000.00
Issuance Date: 09/08/2017
Nr Instances: 1
Nr Exposed: 11
Abatement Date: 10/04/2017
Gravity: 5
Report ID: 0418600
Contest Date:
Final Order: 10/04/2017
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 10/04/2017 | $6,000.00 | 10/04/2017 | Serious | |
| Penalty | Z: Issued | 09/08/2017 | $8,149.00 | 10/04/2017 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct an annual or more frequent inspection of the energy control procedure to ensure that the procedure and requirements of this standard were followed: a) At Southfresh Aquaculture, Eutaw, Alabama: On or about June 5, 2017 and at times prior; the employer did not ensure that machine specific lockout procedures were annually audited/evaluated to ensure that the procedures effectively control all applicable energy sources.
Translate