Violation Detail
Standard Cited: 19260416 A03 General requirements.
This violation item has been deleted.
Inspection Nr: 1560237.015
Citation: 01001C
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/25/2022
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 05/12/2022
Gravity: 10
Report ID: 0316700
Contest Date:
Final Order: 05/16/2022
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/16/2022 | $0.00 | 05/12/2022 | Serious | |
| Penalty | Z: Issued | 04/25/2022 | $0.00 | 05/12/2022 | Serious |
Text For Citation: 01 Item/Group: 001C Hazard:
29 CFR 1926.416(a)(3): Before work began, the employer did not ascertain by inquiry, direct observation, or by instruments, whether any part of an energized electric power circuit, exposed or concealed, was so located that the performance of the work could bring any person, tool, or machine into physical or electrical contact with the electric power circuit: (a) 520 Valentine Lane Bellefonte PA New Residential Homes- The employer did not ensure that the work was conducted in such a way that the Case 300-D excavator could not come in contact with the overhead power line, on or about October 25, 2021. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.