Violation Detail
Standard Cited: 19260858 D Removal of steel construction.
Inspection Nr: 1625428.015
Citation: 01001B
Citation Type: Other
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/24/2023
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 04/19/2023
Gravity: 10
Report ID: 0317500
Contest Date: 04/14/2023
Final Order: 12/11/2023
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 12/11/2023 | $0.00 | 04/19/2023 | Other | |
| Penalty | C: Contested | 04/14/2023 | $0.00 | 04/19/2023 | Serious | |
| Penalty | Z: Issued | 03/24/2023 | $0.00 | 04/19/2023 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1926.858(d): Any structural member being dismembered shall not be overstressed. (a) Hatfield Power Plant, 2773 East Ray Furman Highway, Carmichaels, PA 15320, Precipitation Area on or about September 28th, 2022 at approximately 8:15AM employees were not protected from unplanned sudden collapse of duct work while in the process of dismantling. Relief cuts were made in the duct work resulting in the structural steel becoming overstressed and collapsing.