Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1572166.015
Citation: 01001B
Citation Type: Serious
Abatement Status:
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/01/2022
Nr Instances: 1
Nr Exposed: 7
Abatement Date: 07/22/2022
Gravity: 5
Report ID: 0213100
Contest Date: 08/01/2022
Final Order:
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | C: Contested | 09/27/2022 | $0.00 | 07/22/2022 | Serious | |
| Penalty | Z: Issued | 07/01/2022 | $0.00 | 07/22/2022 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: (a) Paver manufacturing -- On or prior to 1/08/22, the employer had not conducted periodic inspections of energy control procedures (Lockout SOPs) at least annually, for equipment, including but not limited to: Hess Paver Machine, Wiggert Mobilmat 2250 Mixer also includes Material Conveyor Systems, and Color System.