Violation Detail
Standard Cited: 19260451 A01 General requirements.
This violation item has been deleted.
Inspection Nr: 1551284.015
Citation: 01001A
Citation Type: Serious
Abatement Status:
Initial Penalty: $14,502.00
Current Penalty: $0.00
Issuance Date: 02/28/2022
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 03/17/2022
Gravity: 10
Report ID: 0316700
Contest Date: 03/09/2022
Final Order: 11/22/2022
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 11/22/2022 | $0.00 | 03/17/2022 | Serious | |
| Penalty | C: Contested | 03/24/2022 | $14,502.00 | 03/17/2022 | Serious | |
| Penalty | Z: Issued | 02/28/2022 | $14,502.00 | 03/17/2022 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1926.451(a)(1):Each scaffold and/or scaffold component was not capable of supporting, without failure, its own weight and at least 4 times the maximum intended load applied or transmitted to it: a) YORKTOWNE HOTEL RESTORATION PROJECT, SOUTHEAST CORNER OF STRUCTURE - Two employees performed brick restoration services, from a Bennu High Speed Power Unit hydro-mobile scaffold up to ten stories above the grade. The scaffolding system exhibited operational faults, including an inability to descend the climbing masts, which resulted in the scaffold's working surface experiencing a rapid, uncontrolled decent of approximately six stories, on or about August 31, 2021. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.