Standard Cited: 19100217 C01 I Mechanical power presses.
Inspection Nr: 1497027.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $9,446.00
Current Penalty: $4,250.00
Issuance Date: 01/07/2021
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 02/03/2021
Gravity: 10
Report ID: 0336000
Contest Date:
Final Order: 02/01/2021
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/01/2021 | $4,250.00 | 02/03/2021 | Serious | |
| Penalty | Z: Issued | 01/07/2021 | $9,446.00 | 02/03/2021 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.217(c)(1)(i): The employer did not provide and ensure the usage of point of operation guards or properly applied point of operation devices on every operation performed on mechanical power press(es): A.) Tonnard Manufacturing Corporation - On or about 10/1/20, and at times prior thereto, the guards on presses, including, but not limited to, the 24 ton Niagara punch press (Model #A3; #28) were not closed prior to the employee testing a piece of metal when the set up of the equipment was completed. ABATEMENT CERTIFICATION AND DOCUMENTATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation. This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement. IN ADDITION, abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic, or video evidence or abatement or other written records.