Violation Detail
Standard Cited: 19100268 B07 Telecommunications.
Inspection Nr: 1463882.015
Citation: 01001A
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $11,566.00
Current Penalty: $13,494.00
Issuance Date: 03/30/2020
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 06/30/2020
Gravity:
Report ID: 0522300
Contest Date:
Final Order: 04/27/2020
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/27/2020 | $13,494.00 | 06/30/2020 | Other | |
| Penalty | Z: Issued | 03/30/2020 | $11,566.00 | 05/14/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.268(b)(7): Approach distances to exposed energized overhead power lines and parts. The employer shall ensure that no employee approaches or takes any conductive object closer to any electrically energized overhead power lines and parts than prescribed in Table R-2, unless: On or about February 11, 2020, the employer did not ensure a conductive object (strand wire) was not taken closer than the prescribed approach distance in Table R-2 (24 inches) for a 7,200v electrically energized overhead power line.