Violation Detail
Standard Cited: 19100176 B Handling materials - general.
Inspection Nr: 1438531.015
Citation: 01001A
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,570.00
Current Penalty: $3,500.00
Issuance Date: 04/13/2020
Nr Instances: 2
Nr Exposed: 1
Abatement Date: 05/07/2020
Gravity: 5
Report ID: 0336000
Contest Date:
Final Order: 05/06/2020
Related Event Code (REC): A;R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/06/2020 | $3,500.00 | 05/07/2020 | Serious | |
| Penalty | Z: Issued | 04/13/2020 | $7,570.00 | 05/07/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.176(b): Storage of material created a hazard: A.) Erie Strayer Company, 1851 Rudolph Avenue, Erie, PA 16502, Pre-Fabrication Department (Department 50), I-beam drop staging area, west end of the building, on or about October 15, 2019 and times prior there to: I-beams were being stacked flange-on-flange three tiers high, and were not stacked in an interlocking fashion to prevent collapse. An employee sustained a left tibia/fibula fracture when an I-beam that was being hoisted came into contact with the conveyor, kicked-out, and impacted the stack. The I-beam from the stack fell onto the employee's left leg. B.) Erie Strayer Company, 1851 Rudolph Avenue, Erie, PA 16502, Pre-Fabrication Department (Department 50), I-beam drop staging area, west end of the building, on or about October 17, 2019 and times prior there to: I-beams were being stacked flange-on-flange two and three tiers high, and were not stacked in an interlocking fashion to prevent collapse. A total of at least 3 separate stacks were stored in this manner. The condition exposed employees to potential struck-by hazards. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.