Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1697700.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $14,518.00
Current Penalty: $14,518.00
Issuance Date: 03/04/2024
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 03/28/2024
Gravity: 10
Report ID: 0830100
Contest Date:
Final Order: 03/19/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/19/2024 | $14,518.00 | 03/28/2024 | Serious | |
| Penalty | Z: Issued | 03/04/2024 | $14,518.00 | 03/28/2024 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(i):The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a) 379 Boy Scout Rd, Seeley Lake, MT: On or about September 13, 2023, and at times prior, the employer did not conduct an annual inspection of the energy control procedures and evaluate to determine deviations or inadequacies that exposed employees to hazardous stored energy.