Violation Detail
Standard Cited: 19100333 B02 II A Selection and use of work practices
This violation item has been deleted.
Inspection Nr: 1696002.015
Citation: 01001
Citation Type: Serious
Abatement Status:
Initial Penalty: $16,131.00
Current Penalty: $0.00
Issuance Date: 02/09/2024
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 03/28/2024
Gravity: 10
Report ID: 0524530
Contest Date: 03/01/2024
Final Order: 07/31/2025
Related Event Code (REC): A;C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 07/31/2025 | $0.00 | 03/28/2024 | Serious | |
| Penalty | C: Contested | 03/01/2024 | $16,131.00 | 03/28/2024 | Serious | |
| Penalty | Z: Issued | 02/09/2024 | $16,131.00 | 03/28/2024 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.333(b)(2)(ii)(A): Safe procedures for deenergizing circuits and equipment were not determined before circuits or equipment are deenergized. On or about August 14, 2023, safe procedures for deenergizing all electrical energy sources located in the outdoor tank farm metal raceway were not determined prior to employees working to replace/reinstall the conductors. The Active Group Lockout #30 "Tank Farm" procedures did not identify and address the 'Truck Loadout Pump' circuit, energized through circuit breaker #17 in the MSP-3 panel located in the DDE MCC room.