Violation Detail
Standard Cited: 19100119 H03 IV Process safety management of highly hazardous chemicals.
Inspection Nr: 1653785.015
Citation: 01001
Citation Type: Serious
Abatement Status:
Initial Penalty: $14,063.00
Current Penalty: $14,063.00
Issuance Date: 08/25/2023
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 09/21/2023
Gravity: 10
Report ID: 0626700
Contest Date: 09/25/2023
Final Order:
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | C: Contested | 11/16/2023 | $14,063.00 | 09/21/2023 | Serious | |
| Penalty | Z: Issued | 08/25/2023 | $14,063.00 | 09/21/2023 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.119(h)(3)(iv): The contract employer did not assure each contract worker follows safe work practices of the facility: (a) On or about February 28, 2023, in the Marathon Galveston Bay Refinery RHU unit, where the Job Safety Analysis (JSA) did not identify apparent electrical hazards present when the Turnaround Work Scope Approval (WSA) identified damaged conduit and wires.